Following on from T&B’s previously delivered Pharmacy Store and Paediatric Long Term Ventilation Ward schemes for Guy’s and St Thomas’ Hospital NHS Trust, our City Works Division were employed to undertake the phased refurbishment works to form the new Pharmacy Department at St Thomas’ Hospital.
Works included:
• £2,400,000 / 70 week construction programme
• New 24/7operational Pharmacy, Dispensary and Store at St Thomas’ Hospital
• 3-phase internal refurbishment over basement Lower Ground and Ground floors
• Strip-out of existing Pharmacy facility including minor demolition
• Formation of temporary Pharmacy Department with Drug Store and Dispensary
• New Cold Stores and installation of Dispensary Robot
• Full M&E services installation including data, alarm and ventilation systems
• New flooring, partitions, Whiterock, MF & lay-in grid ceilings
• Management of furniture, benching and racking installation
• New clinical washing area and construction of Dispensary Counter
• Full high-quality decoration throughout
• Live hospital and fully occupied environment
• Logistically challenging with restricted deliveries
Here is a few projects we wanted to highlight
T&B delivered £3,100,000 / 36-week CAT-A fit-out wotks to 75,000sq.ft commercial building in Aylesbury comprising office space, toilets, lift lobbies…
£5,000,000 / 74 week phased redevelopment of Bushey Meads School in Hertfordshire alongside Horsley Huber Architects and cost consultants Hookway…
T&B's Interiors team, alongside Academy Consulting and our design partners LSI Architects, delivered the £2,500,000 / 27 week conversion and…
T&B's project delivery team, alongside our design partners DESM and services engineer Fowler Martin and lead consultant Arcadis, have completed…