At T&B we work across all sectors, click on one below to have a look at some of our work...
Phased remodelling and refurbishment of 4th floor within Luton Borough Council’s Grade II Listed Town Hall which comprised open plan offices, staff facilities, breakout area, meeting rooms, toilets and kitchenette.
Key aspects of the works included:
• £450,000 / 20 week construction programme
• Complete remodelling and refurbishment of 4th floor cluster offices to create an open plan office environment
• Refurbishment of entire 3rd floor offices, stores and meeting rooms
• Alterations to WC facilities throughout
• Prayer Room and attached WC facilities with hand and feet wash basins
• Repair and restoration of original Oak skirtings and replacing to match
• New Air Conditioning system installed throughout
Here is a few projects we wanted to highlight
T&B delivered £3,100,000 / 36-week CAT-A fit-out wotks to 75,000sq.ft commercial building in Aylesbury comprising office space, toilets, lift lobbies…
£5,000,000 / 74 week phased redevelopment of Bushey Meads School in Hertfordshire alongside Horsley Huber Architects and cost consultants Hookway…
T&B's Interiors team, alongside Academy Consulting and our design partners LSI Architects, delivered the £2,500,000 / 27 week conversion and…
T&B's project delivery team, alongside our design partners DESM and services engineer Fowler Martin and lead consultant Arcadis, have completed…