T&B’s Interiors team successfully delivered a number of schemes at London Metropolitan University’s occupied campus in Moorgate that include 3rd Floor classroom refurbishment and fit-out of the new Costa Café.
Works included:
• £400,000 / 8 week construction programme
• British Gypsum and Komfire 100 acoustic partitions
• Installation of Ecophon in classrooms and Burgess metal ceilings to café area
• New vinyl flooring and carpet tiles to designed pattern
• Hardwood veneer door sets, skirting and associated ironmongery
• Installation of new M&E services including air conditioning, fire alarm, decorative lighting and data
• High quality and full decoration throughout classroom and café area
• Strip-out of existing canteen and installation of bespoke servery counter
• Formation and fit-out of new Costa Coffee Café and seating area
• New WC and toilet facility
• Live and occupied environment
The project was completed 4 weeks ahead of programmeto the delight of the client.
Here is a few projects we wanted to highlight
T&B delivered £3,100,000 / 36-week CAT-A fit-out wotks to 75,000sq.ft commercial building in Aylesbury comprising office space, toilets, lift lobbies…
£5,000,000 / 74 week phased redevelopment of Bushey Meads School in Hertfordshire alongside Horsley Huber Architects and cost consultants Hookway…
T&B's Interiors team, alongside Academy Consulting and our design partners LSI Architects, delivered the £2,500,000 / 27 week conversion and…
T&B's project delivery team, alongside our design partners DESM and services engineer Fowler Martin and lead consultant Arcadis, have completed…